Milestone Planning

Milestones let you plan and track multi-sprint goals (releases, product versions, major features). Scraut automatically decomposes milestones into epics, tracks health, and generates forecasts.


Creating a milestone

Create a file at:

workspace/milestones/v2.0.md

Format:

# Milestone: v2.0
- Due: 2026-08-31
- Goal: Launch the analytics module with full team support
- GitHub milestone: https://github.com/myorg/my-repo/milestone/2

## Epics
- [ ] Epic: Analytics data pipeline — issues: #55, #56, #57
- [ ] Epic: Dashboard widgets — issues: #58, #59, #60, #61
- [ ] Epic: Export functionality — issues: #62, #63
- [ ] Epic: Team permissions for analytics — issues: #64

## Risks
- Analytics data pipeline depends on backend team delivering the data API (ETA: Sprint 3)
Mitigation: Bob is coordinating with the backend team weekly

## Definition of Done
- [ ] All committed epics closed
- [ ] Analytics dashboard reviewed by 3 internal users
- [ ] Performance: < 3s load for 10k-row datasets
- [ ] Release notes drafted and stakeholders notified

Milestone planning workflow

Trigger: Push to workspace/milestones/*/milestone.md Workflow: milestone-planning.yml

When you push a new or updated milestone file:

push detected (workspace/milestones/v2.0.md changed)

├─ planning_session.py
│ Reads milestone.md
│ Fetches all linked GitHub issues
│ Calculates: total sp, completed sp, projected completion date
│ Calls LLM: "Generate a milestone decomposition and sprint allocation plan"
│ LLM produces: epic breakdown, sprint-by-sprint allocation

├─ Writes .scraut/milestones/v2.0/planning-session.md [BOT-GENERATED]

└─ Posts summary to #scraut-bot

Milestone health monitoring

Trigger: End of each sprint review Workflow: milestone-planning.yml (health check step)

Scraut recalculates milestone health after each sprint:

<!-- BOT-GENERATED — Milestone Health — v2.0 — 2026-06-15 -->

# Milestone Health: v2.0

**Status: ⚠️ At Risk**
**Due:** 2026-08-31
**Current forecast:** 2026-09-14 (14 days late)

## Velocity analysis
- Required: 18 sp/sprint to finish on time
- Recent average: 14 sp/sprint
- Gap: 4 sp/sprint

## Open epics
| Epic | Issues | Closed | Open | SP remaining |
|------|--------|--------|------|-------------|
| Analytics pipeline | 3 | 1 | 2 | 13 sp |
| Dashboard widgets | 4 | 2 | 2 | 10 sp |
| Export functionality | 2 | 0 | 2 | 8 sp |
| Team permissions | 1 | 0 | 1 | 5 sp |

## Recommendation
To meet the deadline:
1. Increase sprint capacity by 4 sp (reduce scope elsewhere)
2. OR defer the "Team permissions" epic to v2.1 (saves 5 sp)
3. OR negotiate 2-week deadline extension

## Risk flags
- Epic "Analytics pipeline" depends on backend API (ETA: Sprint 3) — still pending
→ If API not ready by Sprint 3 end, recommend deferring pipeline epic

The milestone-risk label

When a milestone is forecast to slip more than 1 sprint, Scraut automatically applies the milestone-risk label to related issues. This makes them visible in the GitHub Projects board and Slack alerts.


Scenario: PM spots a milestone risk and responds

Characters: Alice (PM/PO), Charlie (SM)

Week 4 of Sprint 2:

  1. Charlie triggers sprint review
  2. Scraut generates milestone health report: v2.0 is 14 days behind forecast
  3. Slack post in #scraut-bot: "⚠️ Milestone v2.0 at risk — forecast slipped to Sep 14"
  4. Alice reads the health file: sees the analytics pipeline epic is blocked by the backend team
  5. Alice updates workspace/milestones/v2.0.md:
    • Moves "Team permissions" epic to v2.1
    • Notes the scope reduction in the Risks section
  6. She commits and pushes
  7. Milestone planning workflow re-runs: updated forecast is Aug 28 (on time!)
  8. milestone-risk label removed from issues

Time: 15 minutes async. No milestone meeting needed.